Work accomplished in the first half of 2024

In the first half of 2024, Uzbekneftegaz JSC achieved effective results in the targeted use of hydrocarbon fields, increasing the production of natural gas and liquid hydrocarbon raw materials, ensuring the uninterrupted operation of existing wells, opening new fields, and modernizing production capacities.

To achieve hydrocarbon production targets during the past period, 43 wells were drilled.

In order to study the gas prospects of the deep Jurassic deposits in the Ustyurt region, for the first time in the history of Uzbekistan, the final stage of drilling is being conducted at a depth of 5500-6500 meters at well No. 11 of the "Nizhny Surgil" field, well No. 1 of the "Sarizhol" field, and well No. 1P of the "Western Nizhny Surgil" field.

Additionally, major repairs were carried out on 40 wells and 20 technological measures were implemented. In particular in cooperation with specialists from the Chinese company "Jereh" 5 small compressor stations were put into operation at the "Shurtan" field.

Four preliminary gas treatment plants were built and put into operation at the fields. To ensure the stability of natural gas transportation in the gas transportation system, 56.4 km of gas pipelines were built.

846.7 thousand tons of hydrocarbon raw materials were processed, producing 525.9 thousand tons of automobile gasoline, 307.6 thousand tons of diesel fuel, including 184.3 thousand tons of GTL diesel fuel, 98.3 thousand tons of aviation kerosene, 50.9 thousand tons of GTL kerosene, and 121.5 thousand tons of GTL naphtha.

In January-June of this year, 333.3 thousand tons of liquefied gas were produced, forecast was fulfilled by 109.7 percent.

“Uzbekneftegaz” JSC Information Service